Show solutionHide solution
Question 4
Normalize catalyst productivity
A batch with 0.00200 mol total catalyst produces 0.500 mol product in 100 s. Define turnover number as product moles divided by catalyst moles and average turnover frequency as that number divided by elapsed time. Assume one product molecule per turnover.
Diagram shown in the original SVG worksheet.
Find turnover number and average turnover frequency based on total catalyst.
If only half the catalyst sites are active throughout, find the active-site-normalized frequency and explain why this is an average, not an initial rate.
Question 4 - Solution
Normalize catalyst productivity
Diagram shown in the original SVG worksheet.
(a) Reasoning and result
Turnover number is . Average frequency is s.
(b) Analysis
Active catalyst is 0.00100 mol, giving s. Product accumulated over 100 s averages any rate changes; it does not specify the initial slope.
Check and interpretation
Turnover greater than one demonstrates repeated productivity under the model, not complete proof of an unchanged catalyst structure.